SHOTS - CONSTRUCTION MANAGEMENT & PLANNING

💥 PERT technique of network is mainly useful for research and development projects. 

💥 Expected project duration generally follows normal distribution curve. 

💥 Site being located does not represent the activity. 

💥 Critical path is always longest. 

💥 Cost slope=(Cc-Cn/Tn-Tc). 

💥 The direct cost of a project with respect to the normal time is minimum. 

💥 The reduction in project time normally results in increasing the direct cost of the project and decreasing the indirect cost. 

💥 Economic saving of time results by crashing the cheapest critical activity. 

💥 The process of changes and rescheduling or re planning called updating. 

💥 Slack time refers to an event. 

💥 Slack time in PERT analysis is minimum for critical events. 

💥 Interfering float results in total float and free float. 

💥 Activity is resource consuming, event is instantaneous stage. 

💥 Dummy is a resource less element. 

💥 Sheep foot roller most suitable type of equipment used on clayey soil. 

💥 Batching refers to the controlling the quantity of each material into each batch.